Omnis were privileged to be part of this award winning major electrical sub-station built in a contemporary style to stringent planning requirements in keeping with the theme of the adjacent science park.

Works including a complex steel framed / steel clad / masonry structure featuring a curved standing seam ‘Kalzip’ roof. The building itself houses four grid and distribution transformer each contained within substantial reinforced concrete structures together with split level control rooms and amenity facilities.

Specialist mechanical and electrical installations have been incorporated including the installation of a fully automated high pressure water fire suppression system.

• Client: EDF / Carillion Utilities Services Ltd
• Value: £3.5m
• Duration: 75 weeks